My project chargeback report is alwsys empty

hi
My project chargeback report is alwsys empty, but the vm charge back report shows actual records.


My project chargeback report is configured as follows:

Anyone can help me? Thank you!!

Hi, @wangxiangyu
Did you enable capturing metrics?
How to do it, find here http://manageiq.org/documentation/top-tasks/#collecting-capacity-and-utilization-cu-data

@arnika_sky
I misused the “Chargeback for Projects” which is used for kubernetes. I should use “Chargeback for Vms” to generate chargeback report of vms for openstack and vmware.